This is the discussion forum for this question. If you find any mistakes in the solution, or if you have a better solution, then this is the right place to discuss. A healthy discussion helps all of us, so you are requested to be polite and soft, even if you disagree with the views of others. The question and its current solution has also been given on this page.

Advertisement

Question

A can harvest a field in 18 days. B can do the same work in 11 days. How much did A get if the farmer pays them a total amount of Rs. 7200 for a work that they together completed in 6 days?

A

Rs. 2400.

B

Rs. 2500.

C

Rs. 2300.

D

Rs. 2700.

Soln.
Ans: a

Work done by A in 1 day = $1/18$. So the work in 6 days = 6 × $1/18$. His share is Rs. 6 × $1/18$ × 7200 = Rs. 2400.