This is the discussion forum for this question. If you find any mistakes in the solution, or if you have a better solution, then this is the right place to discuss. A healthy discussion helps all of us, so you are requested to be polite and soft, even if you disagree with the views of others. The question and its current solution has also been given on this page.

Advertisement

Question

Mr. X can finish a task in 13 days. Mr. Y can do the same work in 8 days. What is the ratio of the efficiencies of X : Y?

A

${8/13}$.

B

$1{8/13}$.

C

${2/3}$.

D

${9/14}$.

Soln.
Ans: a

The efficiency of X is $100/13$%, and the efficiency of Y is $100/8$%, so the ratio will be $8/13$